Monday, 31 May 2010

The progress so far

Our slab was laid almost 6 months ago. Thanks to our steel frame/ structural steel supplier the build has been moving at a super slow pace and we are still waiting on the remaining trusses that are currently on their way to Adelaide.

Hebel PowerFloor

Boral Jarrah bricks with off white mortar.


Our Stegbar windows, in white birch.

Our slab was laid in mid August, almost 9 months ago :(

No comments:

Post a Comment